Phase 1 W & NW Sanitary Sewer Expansion Project
Who is required to connect the LPSD sanitary sewer system?
All properties within 1,000 feet the ordinary high water level of Lake Poinsett is under the jurisdiction of the LPSD and therefore, per LPSD ordinance, is required to connect to the LPSD system, once it becomes available. Additionally, homes within 400 feet of an existing LPSD sanitary sewer line are also required to connect.
Why is the LSPD doing the project now?
As outlined in the Lake Poinsett Management Plan, water quality is a main concern and the LPSD was created to aid in the effort of keeping Lake Poinsett clean by completing a sanitary sewer system around the lake. Also, the longer the LPSD waits on completing the system, the more expensive it is going to get.
Are there opportunities for additional grant funds?
First District Association of Local Governments and the SD DANR have both indicated that additional grant funds are unlikely.
Is the land cost for the future lagoon included in the project cost?
No, the land for the lagoon location was purchased by the LPSD in 2024. Only the construction of the lagoon is included in the project estimate.
What is the timeline?
As of April 2026, the schedule is for the engineering survey and design to likely begin fall of 2026 and continue into 2027 for the project to be bid. Construction may begin later in 2027 and be completed in 2028 to early 2029.
What is this going to cost me?
The monthly sewer rate has not yet been determined. This will be calculated more accurately as the LPSD works with the DANR to finalize the project funding. Past LPSD sewer expansion projects have included a fixed connection fee set by the Board. The current LPSD residential rate $82 per month.
How will my property be connected?
It depends on where the mainline is located, but the intent would be for the sanitary sewer connection to begin at the location of the existing septic tank and go straight to the mainline.
What happens to my existing septic tank and drain field?
Generally, the septic tanks are demolished and filled in. Drain fields may be abandoned or removed depending on the location of new sewer pipes.
What happens to my lawn or property after construction?
Past LPSD sanitary sewer projects have included installing new sewer service pipe from the collector main to a point of connection on the existing sewer service line past the demolished septic tank. Repairs would include replacing any pavement, grass, landscaping, etc. that was disturbed during construction.
Will there be a gravity line or a pump for each home?
This will be determined for each residence during design. Past LPSD expansion projects have included a combination of gravity service connections and pumped service connections based on the elevation of the home and the depth of the proposed sanitary sewer mainline.
How deep will the pipe be placed in ground?
This will be determined during design, but generally the gravity sewer mains are a minimum of 8-feet deep. Maximum depth is determined by a combination of soil and site conditions along with cost considerations.
Will this expense and effort actually result in better water quality?
The effect is admittedly hard to measure, but from the standpoint that there will no longer be septic systems with drain fields that seep into the ground, there will be less effluent that can potentially reach the lake.
Who is responsible for maintenance costs and repairs?
The LPSD owns and maintains the system from the sewer mains to the point of connection from the existing services and is responsible for all operation and maintenance expenses.
How many permanent residents and how many commercial properties are there in the 118 connections?
The assumption is that roughly 30%, or approximately 40, residents are permanent, when looking at Hamlin County data of who has a mailing address of West Lake Drive. There are no known commercial accounts in the Phase 1 project area at this time.